Documenting delays: weather, client decisions, backorders

Document a delay the day it starts: one row with the job, the date, the cause, what happened, the estimated days lost and who owns the fix, then a short written note to the client and an updated schedule. Most schedule fights start with a delay nobody wrote down.

Free download: Delay log (Excel). One row per delay with cause, days lost, who was notified, when and how, and whether the client confirmed in writing. It flags delays with no written notice to the client, notice later than your own setting, client decisions with no written OK, backorders with no new delivery date, change orders needed with no change order number, blank days lost and open delays with no end date. A Start Here sheet totals it all. The example rows are labeled; delete them before you start. No email required.

1. Why delays turn into schedule fights

A job slips a day for rain, three days waiting on a tile choice, a week for backordered windows. Each one feels small, so nobody writes it down. At the end the client sees a job that finished late and remembers none of the reasons. A short written record, made when each delay happens, lets you explain the schedule from facts instead of memory.

2. One row per delay

Keep one list (a spreadsheet is fine) with one row for each delay:

3. Write it the day it starts, and keep it factual

Note the cause and what you saw the same day, ideally in the daily log and then in the delay list. Stick to what happened, when, and who said what. Leave out blame. A delay that is written down when it starts is much easier to explain than one pieced together at the end of the job.

4. Tell the client in writing

A phone call or a talk on site is a good start, but follow it with a short written note: an email, a text or a message in whatever app you use. Say what happened, the cause, the estimated days, what you are doing about it and, if you need something from the client, what and by when. Keep a copy with the job. How much notice your contract calls for, and whether a delay gives you more time or money, is set by your contract; ask an attorney about your situation. Pick your own target (for example, within a couple of days) and track it.

5. The three common causes

6. Update the schedule and the subs

Every delay moves something. Update your 2-week lookahead and tell the subs whose dates moved. A short weekly update to the client built from the delay list keeps everyone on the same page; see updating clients and subs without PM software.

7. Close each delay

When the delay is over, fill in the end date and the actual days lost. If it needed a change order, enter the number once it is signed. An open delay with no end date is easy to forget and hard to explain later.

8. A ten-minute weekly review

Once a week, check: delays with no written notice to the client, client decisions still waiting on a written OK, backorders with no new date, change orders not written yet and open delays. Fix what you can while it is fresh.

Where an assistant helps

The hard part is remembering to send the written note while the job keeps moving. During the pilot, we flag a delay with no written notice to the client and draft a short update for your office to approve. We set it up one piece at a time, and a real person reviews everything.

Free 60-day pilot: keep working in your own phone, email and Google Sheet. Request a pilot spot.

More guides

Frequently asked questions

What should I write down when a construction job is delayed?

The job, the date it started, the cause (weather, homeowner decision, backorder, inspection, sub no-show, change order), what happened in a few facts, the estimated days lost, who owns the fix, when and how the client was told, whether they confirmed in writing, and whether the schedule and any change order were updated.

How soon should I tell the client about a delay?

As soon as you know, and in writing. Any notice period you must meet is set by your contract; ask an attorney about your situation. Many builders set their own target, such as within a couple of days, and track it.

Is a phone call enough to notify a client of a delay?

A call is a good start, but follow it with a short written note (email, text or app message) that says what happened, the cause, the estimated days and what you need from the client, and keep a copy with the job.

What if the delay is caused by the homeowner's decision?

Write down when you asked, when you needed the answer and what slipped. Get the client's OK in writing, and if the decision changes scope or price, write a change order.

Does documenting delays give me more time on the contract?

This is general information, not legal advice. Whether a delay gives you more time or money is set by your contract; ask an attorney. A clear, same-day record may help explain the schedule either way.